The Job-Shop problems considering material transit time and machine set-up time were studied. During the optimization and calculation, the material transit time and the influences on the Job-Shop scheduling were taken into account. Subsequently, the solution method was provided and the Job-Shop scheduling problem was solved using hybrid PSO algorithm combining GA and SA. Finally, the analysis and calculation of interaction between material transit time, machining time and machine set-up time was carried out by the simulation based on real conditions. The results show that the proposed method considering the machine set-up time and material transit time is more feasible and realistic than the scheduling which appends the material machining time directly.
參考文獻
相似文獻
引證文獻
引用本文
葛茂根,劉明周,張明偉,蔣增強,張銘鑫.計及機器調(diào)整和物料運送時間的Job-Shop調(diào)度算法[J].農(nóng)業(yè)機械學(xué)報,2008,39(11):127-131.[J]. Transactions of the Chinese Society for Agricultural Machinery,2008,39(11):127-131.